Sure, here they are.
Inspector, 02:14:
Rebar spacing at the north footing is over 12 inches. Needs extra bars before the pour.
Inspector, 06:12:
Vapor barrier lap is short along grid C, and two anchor bolts are missing at the garage wall. I added all three to the Hillcrest punch list and tagged the framing crew.